mark_h
9th August 2002, 01:21
The background is that we have 3 sites and 1 financial and loogistic company. Splitting them will not be allowed. We are on 4c3 and have the a&d extension.
Now the problem is that we have the same part that is buy at two sites and make at one site. The typical part like this is buy on the item master and make on the group item. The problem is that the leadtime is kept on the item master. GRP and all of our reports use the item master to get the leadtime. The problem is that the planning and reports are pulling the leadtime for a buy part, in somecases this can mean a difference of 200 days.
The only solution I have come up with so far is to
add the leadtime to the maintain group item master session. This would be done using a new table and qkey. Then I would change our reports to use the leadtime from the new table. AND I would copy this leadtime into the item master before each GRP run for a project group. Not a pretty solution and was hoping for a better idea from someone in this group.
There are a bunch of reasons why parts differ from site to site, but mainly 2 sites are new manufacture and 1 site is overhaul. So a overhaul part X is not the same as a new part X. Even on some parts that are purchased at all three sites the leadtimes are different(different vendors). So any ideas out there?
Mark
Now the problem is that we have the same part that is buy at two sites and make at one site. The typical part like this is buy on the item master and make on the group item. The problem is that the leadtime is kept on the item master. GRP and all of our reports use the item master to get the leadtime. The problem is that the planning and reports are pulling the leadtime for a buy part, in somecases this can mean a difference of 200 days.
The only solution I have come up with so far is to
add the leadtime to the maintain group item master session. This would be done using a new table and qkey. Then I would change our reports to use the leadtime from the new table. AND I would copy this leadtime into the item master before each GRP run for a project group. Not a pretty solution and was hoping for a better idea from someone in this group.
There are a bunch of reasons why parts differ from site to site, but mainly 2 sites are new manufacture and 1 site is overhaul. So a overhaul part X is not the same as a new part X. Even on some parts that are purchased at all three sites the leadtimes are different(different vendors). So any ideas out there?
Mark