ericthomas
25th July 2002, 17:53
Dear All,
One of our Business Analyst told that PMC module can installed in C3 with out going to C4.
To my knowledge
1. PMC is part of C4 and higher tools.
2. Simply tools cannot be upgraded to C4 without the actual migration procedure.
3.If c4 tools updated then VRC c4 would replace c3,c2,c1 effectively. I dont know whether we can keep the c3,c2,c1 and still derive the existing custome layer from there.
Could you give some answers to these assumptions?
thanks in advance
Eric.:confused:
One of our Business Analyst told that PMC module can installed in C3 with out going to C4.
To my knowledge
1. PMC is part of C4 and higher tools.
2. Simply tools cannot be upgraded to C4 without the actual migration procedure.
3.If c4 tools updated then VRC c4 would replace c3,c2,c1 effectively. I dont know whether we can keep the c3,c2,c1 and still derive the existing custome layer from there.
Could you give some answers to these assumptions?
thanks in advance
Eric.:confused: