Hi,
When we upgraded from FP2-Fp3.we upgraded both application and tools.When we are running Data Upgrade Engine (ttspt1200m000) session and getting the below error messages
à Process 6 - Fatal error: No license to run object '/erpsol/bse/application/tcB61U_a_stnd/otccom/ocom4500' (product 7115).
à 1: process 7 - Fatal error: Error 606 (Reference does not exist) on tcmcs013100 in select
2: process 7 - Fatal error: Can not continue in ttspt1200m000 in DLL: otcsptdll1911 (payment.schedule.present) [sql.fetch]
3: process 7 - Error: ttspt1200m000: A not terminated transaction is aborted (payment.schedule.present () in object otcsptdll1911)
Please help in solving this issue ASAP.
Thanks & REgards,
Vaishali
When we upgraded from FP2-Fp3.we upgraded both application and tools.When we are running Data Upgrade Engine (ttspt1200m000) session and getting the below error messages
à Process 6 - Fatal error: No license to run object '/erpsol/bse/application/tcB61U_a_stnd/otccom/ocom4500' (product 7115).
à 1: process 7 - Fatal error: Error 606 (Reference does not exist) on tcmcs013100 in select
2: process 7 - Fatal error: Can not continue in ttspt1200m000 in DLL: otcsptdll1911 (payment.schedule.present) [sql.fetch]
3: process 7 - Error: ttspt1200m000: A not terminated transaction is aborted (payment.schedule.present () in object otcsptdll1911)
Please help in solving this issue ASAP.
Thanks & REgards,
Vaishali