ganesh_kapase
19th June 2005, 10:02
Hello Everybody,

Plz tell me how to change the Package Combination of the Company even though the physically tables are present in the company. I had tried through the session "Maintain Companies (ttaad1100m000)" but could not allow to change the pkg.combination.

Plz advice ASAP.


GANESH

Markus Schmitz
20th June 2005, 12:36
Baan does not allow to simple change the package comb. of a company in maintain companies due to good reasons. If the new package combination hase a different data dict, then change need to be applied to a new company.

This is what above session (ttaad1101m000) does. You find it in tools, Application configuration, misc.

Regards

Markus