amitkumar
5th August 2010, 08:35
Dear All,

I have one Scenario of Invoice Type as " Unit Rate".
Project:- Contract Type as " Fixed Price Contract "
Invoice Type as " Unit Rate".
Controlled by and Budget by a " Activity".
Project Business Partner - Amount is not defined

In the Activity , i have choosen Progressive Based Invoicing as " No" , this allowed me to insert only the Pysical progress Quantity but not the sales rate.
My query to all is 1) Can we invoice ? 2) if Invoicing is possible what amount will the system take and from where ?

Please help me finding the solution

Regards

hotjens
9th August 2010, 17:41
For at least one of the activities you should have Progress based Invoicing set to Yes. If you don't flag an activity why bother about unit rates in the first place. Than capturing progress by activity you could invoice this for the sales rate defined times the quantity.

Senthil Kumar R
13th August 2010, 13:48
Hi,

Progressive Based Invoicing should be 'Yes' as the definition of unit rate is "Invoicing method based on the progress and element/activity sales rate per unit. Invoices are booked against the contract amount with installments."
The unit rate invoicing is calculated as the number of units completed * the sales rate given in the activities or element session.

Senthil Kumar R
Coserve Solutions