11th January 2010, 08:43
Hi,

Can we generate PRP Order for Equipment as Cost order and how?.

Thanks

Senthil Kumar R
11th January 2010, 11:12
Hi,

If your requirement is to rent(hire) an equipment from a supplier, and not to by a equipment itself. then just check the check box in session standard equipments (tppdm0512m000) secondary session Standard equipments (tppdm0112s000) session 'option' tap external equipment.

if you don't want to declare there even in the budget {activity budget (equipment)tpptc2112s000) genral tap the external equipment check box can be checked. and when PRP is excuted, it generates order for rent.

ac1974
12th January 2010, 07:43
Thanks

I had checked for external equipment in session Standard equipments (tppdm0112s000).

My budget is by element and control by activity .

Now i want to genertae cost order through PRP .

When we transfer the order , the avaliable order type is only for material and not cost.

So how to generate cost order .