Senthil Kumar R
18th November 2009, 11:28
Hi All,

When a project is Budgeted by Element and controled by Activity, in estimation we are linking them. but how to support the activity base line for different element start and end dates.

Regards,
Senthil Kumar. R

hotjens
3rd December 2009, 17:19
Baselines will only save dates for activities and milestones. No element dates can be baselined.

Senthil Kumar R
7th December 2009, 17:12
Yes, it is correct, but my requirement is in Budgeted by Element and Controled by Activity we can link same activities to multible elements. In that case how to support the activity start date and end date for the one activity linked to different elements?

hotjens
14th December 2009, 09:30
Hi,

there is no relation to elements, so if the baseline is saved it stores the dates of the activity irrespective of any links to elements. Whether it is not linked, linked once or multiple times will not matter.