I have question :
How to set up Project so we can Inovice base on Material Delivery and Activity Progress ?
as I know if we want to invoice base on Material Delivery (tppin4557m000) we choose Cost Plus for Invoice Type, but we can not invoice base on Activity Progress.
Otherwise if we want to invoice base on Activity Progress (tppin4551m000) we choose Progress Invoice for Invoice Type, but we can not invoice base on Material Delivery (tppin4557m000).
I want to Invoice base on both Material Delivery and Activity Progress

Thank you

Ian

ianymni
27th May 2008, 05:31
Do not put Your Advertise here . This room is use for Baan knowledge. Administrator, please do not allow any advertisement in here.

EdwinvdBorg
27th May 2008, 08:39
Dear ianymni,

I have already informed the BaanBoard Administrator and requested him to delete the post from this guy.
This should be taken care of today.

ianymni
27th May 2008, 10:24
Dear Moderator


Thank you for your help and understanding

Best Regards

Hotma P

hotjens
28th May 2008, 09:26
Use the project for the activity progress based invoicing and handle the material delivery via an extension specificly created for this purpose. THere is no other option I know that can be used.