Sri_baan
26th November 2001, 17:15
Hi,
Let me explain the situation abt the Provisional Amounts.
We Include an amount (Sundry Costs) in the Budget for an Element (created specially to include this Amount) which takes care of the things (Costs) which are not able to include during the tendering stage. This amount we call as Provisional Amount.
During Execution of the Project, if we come across any kind of work For Eg. Breaking of Rock which has come during Excavation.
This extra cost of breaking of Rock has to be taken from the Provisional Sum ( which is allready included in the Project Contract Amount)
It is not a Variation becoz in one of the Elements, the breaking of Rock Cost is inlcuded but only appoximate.
Pl tell me whether I can use the Baan Provisional Amount functionality for the above requirement.
Regards
Sridhar
Let me explain the situation abt the Provisional Amounts.
We Include an amount (Sundry Costs) in the Budget for an Element (created specially to include this Amount) which takes care of the things (Costs) which are not able to include during the tendering stage. This amount we call as Provisional Amount.
During Execution of the Project, if we come across any kind of work For Eg. Breaking of Rock which has come during Excavation.
This extra cost of breaking of Rock has to be taken from the Provisional Sum ( which is allready included in the Project Contract Amount)
It is not a Variation becoz in one of the Elements, the breaking of Rock Cost is inlcuded but only appoximate.
Pl tell me whether I can use the Baan Provisional Amount functionality for the above requirement.
Regards
Sridhar