9th December 2007, 14:43
Hi,

I was using in baan iv hours accounting in project module. e.g tphrs1100m000
I could not find in BaaN LN 6.1 .

Please advice how to track the project man hours in the BaaN Ln. what is the session code.

Thanks in advance.

b98

hotjens
10th December 2007, 08:26
Hi,

the equivalent to HRS is now part of the People module. The specific session to look for: bptmm1800m000. This is an umbrella session that will allow you to select what kind of hours you would like to enter. Select the Project option, bptmm1111m000. Don't forget to flag Project as an implemented software component in tccom0500m000.

Good luck!

baan98
10th December 2007, 12:00
Thanks.. I Have Already Checked And It Is Same. It Is Working Fine.

B98