amyumyun
17th November 2005, 17:10
Hello,
We use BaaN IV Big Projects and I have a question related to using of the standard and project items.
I'll try to explain the situation with an example:
We have two active projects: Project A and Project B
We use Item A in both of them!
On the 20th of November we buy the Item A - 1 kg. * 20 000 usd and we will use it in Project A
On the 20th of December we buy (again) the Item A - 1 kg. * 25 000 usd and we will use it in Project B
Note: We have not used the Item A for Project A, yet. It's still in the warehouse.
If I buy and maintain the receipt on 20th of December in any warehouse the system will calculate the average cost price and I will issue the Item A with average privce to Project A and Project B- 22 500 usd, but I shouldn't use the average price. I should use the purchase price!
How can I avoid this inconvenience and in the same time to use the warehouses?
Thank you!
We use BaaN IV Big Projects and I have a question related to using of the standard and project items.
I'll try to explain the situation with an example:
We have two active projects: Project A and Project B
We use Item A in both of them!
On the 20th of November we buy the Item A - 1 kg. * 20 000 usd and we will use it in Project A
On the 20th of December we buy (again) the Item A - 1 kg. * 25 000 usd and we will use it in Project B
Note: We have not used the Item A for Project A, yet. It's still in the warehouse.
If I buy and maintain the receipt on 20th of December in any warehouse the system will calculate the average cost price and I will issue the Item A with average privce to Project A and Project B- 22 500 usd, but I shouldn't use the average price. I should use the purchase price!
How can I avoid this inconvenience and in the same time to use the warehouses?
Thank you!