Hi,
As every one will agree that BaaN IV c4 Estimate is very difficult to enter .
Is there any way to from excel to BaaN estimate module to transfer via schema or import facility.is there any standard sessions is available.
Our process acitivity:
1.proposal engr prepares on excel for project item.
2.manually sent to project team member.
3. project team member insert in element budget options for equipment,material,sundry,labour details .
we tried to use the estimate module options i.e formating structure,inserting item level lines .. etc but it is very tidious.
can any one as come with short cut method or any schema available.
please let me know.
As every one will agree that BaaN IV c4 Estimate is very difficult to enter .
Is there any way to from excel to BaaN estimate module to transfer via schema or import facility.is there any standard sessions is available.
Our process acitivity:
1.proposal engr prepares on excel for project item.
2.manually sent to project team member.
3. project team member insert in element budget options for equipment,material,sundry,labour details .
we tried to use the estimate module options i.e formating structure,inserting item level lines .. etc but it is very tidious.
can any one as come with short cut method or any schema available.
please let me know.