mahadevan
11th November 2004, 11:25
Hi,
We are using BaaNIVc4 system. I want to make budget adjustment in the project module.(tpptc0170m000) the sysem gives message the status should be made as final to insert the record. cuurently the status is as actual.

if change i change status to final and insert the adjustment will this adjustment entry will show separate entity in the baan system or is there any other solution is available.

what is the impact in project and finance module.

please advice.

EdwinvdBorg
11th November 2004, 12:38
Hi,

You can only use Budget Adjestments in tpptc when the status is "Final". As long as this is still "Actual" you will not be able to use Budget Adjustments.
This is standard functionality and will also give the correct transactions in Project, Finance and other areas in BAAN IV.

Go to a test environment and see for yourself.

Regards,

Edwin

Ulrich Hofmann
25th November 2004, 11:25
Hi,

To work with adjustments you need to specify the elements being effected by a change (assuming, you work with an element structure)

Then, change the element status to final (one or more elements in the structure)

Maintan the Adjustment and select the elements hat need to be changed.

You will be able to see the budget effect the change has coused.

But, in finance you will only see increased costs for changed costs. You will not see an adjustment code in finance. Only if you can add an Extension (additional contract!!) you would see the change there.

If you can not use extensions but you like to see changes in finance, you might consider operating with different cost objects (control code!)
But this would increase the number of cost objects!

If you have more questions or discuss in more detail, send me a note.


Ulrich Hofmann
www.pms-c.de














Hi,
We are using BaaNIVc4 system. I want to make budget adjustment in the project module.(tpptc0170m000) the sysem gives message the status should be made as final to insert the record. cuurently the status is as actual.

if change i change status to final and insert the adjustment will this adjustment entry will show separate entity in the baan system or is there any other solution is available.

what is the impact in project and finance module.

please advice.

mahadevan
30th November 2004, 06:19
Thanks.. I will try .