3rd April 2002, 10:21
In Maintain Activities session, we register the Progress & the Actual Start Date.
Then after Generating Network Plan, the Planning Board should take this Actual Start, the % Progress of the Activity and the Progress Date of Plan then accordingly Schedule the Plan.

But In my case, After Generating the Network Plan, the Planning Board Dates and the Early Start Date are no where near the Actual start Date.( not able to make out any relation between the dates)

" BaaN help! says that it will consider the Actual Start Date and the % Progress and give the Planning board date accordingly with the remaining duration of the Activity with reference to the Plan Progress Date.

Has anyone come across this problem?
Thanks for the early reply.

Sridhar Joshi