cherokee
31st March 2004, 17:41
Hello Everyone,

When you start working in to a Service order (status in progress) and you realize that you will need more mateials that were estimated at the begin(and you are short on that material), once the Service Order is in Progress, you can not add any new items in estimated materials session(tssma3170m000). Why in estimated materials session? It is the only why let MRP looks at this new requiements and generate supply. If I enter it in Actual Materials session(tssma3110m000), no demand is generate it when MRP runs.

How can I generate new demand for a Service Order once it is in progress? Where MRP can sees it.

Carlos