donnie
25th February 2004, 12:21
During connection between Baan V and MS Project I' ve got these problems:
- Charge element defined in Baan as Work Package are imported in MSP with blank description in the column CE type;
- If I create in MSP a CE Element and import it in Baan and then re-import it in MSP the column CE type became blank;
- If I disconnect the project and try to modify the CE in MSP the program gives the message "An invalid CE elemant has been selected"
The import function I refer to is the synchronization between of ChBs/Budget/Schedule
Is there anyone who can help me?
- Charge element defined in Baan as Work Package are imported in MSP with blank description in the column CE type;
- If I create in MSP a CE Element and import it in Baan and then re-import it in MSP the column CE type became blank;
- If I disconnect the project and try to modify the CE in MSP the program gives the message "An invalid CE elemant has been selected"
The import function I refer to is the synchronization between of ChBs/Budget/Schedule
Is there anyone who can help me?