Andreas
20th March 2003, 12:53
Hi,
i have the folowing problem:
I'm on Vc.
We have a routing with a routing unit that is different from 1 (suppose 100).
In this routing we have some tasks with fixed duration time (suppose 100 min).
When we plan a production order via cp or even manually maintain a production order
for an item with this routing, then the production time for this routing is given
as fixed duration time divided by routing unit in production planning.
In our case the time is 100 min / 100 = 1 min.
In my opinion this is wrong (PEG says this is standard functionallity).
Fixed duration time is fixed duration time! no matter if routing unit or lot size
is 1, 2, 3 or 10000.
Now my question to people who are on Baan IV:

Is the funtionality the same or is it different?

Paul P
25th March 2003, 03:02
Dear Andreas,

BaanIV doesn't support fixed duration production operation by default. You need a work around in BaanIV to model that

Rgds,
Paul