Bryan
13th November 2002, 23:44
We have 2 major levels in our BOM - a finished good and a subassembly. Our subassembly is basically a finished good without labels. So, we could have, for example, 5 different finished goods that all call out the same subassembly.
In terms of routing operations, the subassembly level is where 95% of the production time occurs. The last operation on the routing for the subassembly is curing, where the parts sit in a room for a couple days.
There is a disconnect between the quantities ordered at the finished good level and the quantity built at the subassembly level. Example - one of our finished goods is ordered in quantities of 45, but the subassembly level must be built in multiples of 50.
lets say a customer orders 45 of the finished good part. We would then open up 2 production orders, one for 45 of the finished good, and one for 50 of the subassembly. We would build the subassembly, put all 50 to stock, then issue 45 to a finished good production order, build that, report production complete and ship the order. The 5 extra subassembly parts would remain in stock until a new finished good production order needs them.
The problem with the above scenario is that since about 95% of the lead time is in the subassembly level, it is very hard for our sales and shipping groups to be able to accurately peg down from the sales order to the \ finished good level to the subassembly level to determine when product is coming to stock. I guess this is the disconnect due to having 2 levels in the BOM.
I have considered setting the subassembly as a phantom, but the problem is that when the customer orders 45, and we need to build 50, then there is no way to put the 5 extra units into stock at the subassembly level - which we need to do because we do not want to label them.
Has anyone ran into a similar issue? Basically the problem is that we have these 2 major levels in our BOM, and because the bulk of the lead time is at the subassembly level, and because we are not using projects and there is no 1:1 correlation between finished good and subassembly order, we have to jump through hoops trying to determine when each order will come to stock.
We basically have multiple sales order lines, all which could be different finished good production orders, which all could be calling out 1 subassembly order - and trying to figure all this out so we can schedule shipping and inform our customers on order status is a nightmare.
Thanks
Bryan G
In terms of routing operations, the subassembly level is where 95% of the production time occurs. The last operation on the routing for the subassembly is curing, where the parts sit in a room for a couple days.
There is a disconnect between the quantities ordered at the finished good level and the quantity built at the subassembly level. Example - one of our finished goods is ordered in quantities of 45, but the subassembly level must be built in multiples of 50.
lets say a customer orders 45 of the finished good part. We would then open up 2 production orders, one for 45 of the finished good, and one for 50 of the subassembly. We would build the subassembly, put all 50 to stock, then issue 45 to a finished good production order, build that, report production complete and ship the order. The 5 extra subassembly parts would remain in stock until a new finished good production order needs them.
The problem with the above scenario is that since about 95% of the lead time is in the subassembly level, it is very hard for our sales and shipping groups to be able to accurately peg down from the sales order to the \ finished good level to the subassembly level to determine when product is coming to stock. I guess this is the disconnect due to having 2 levels in the BOM.
I have considered setting the subassembly as a phantom, but the problem is that when the customer orders 45, and we need to build 50, then there is no way to put the 5 extra units into stock at the subassembly level - which we need to do because we do not want to label them.
Has anyone ran into a similar issue? Basically the problem is that we have these 2 major levels in our BOM, and because the bulk of the lead time is at the subassembly level, and because we are not using projects and there is no 1:1 correlation between finished good and subassembly order, we have to jump through hoops trying to determine when each order will come to stock.
We basically have multiple sales order lines, all which could be different finished good production orders, which all could be calling out 1 subassembly order - and trying to figure all this out so we can schedule shipping and inform our customers on order status is a nightmare.
Thanks
Bryan G