noorulhaq
19th September 2002, 08:24
hi,

We have routing defined for an item A which consist of
four operations.
Backflushing will be done automatically. No hours accounting.

The four operations are

1. Cutting
2. Welding
3. Carpentary
4. Fabricating

Most of the cases, the operations will be performed sequencially. So we dont face problem to complete each operations.
But some cases, more than one operation will start simultaniously like (1)cutting of metals and (3)carpetary for wood works will start in the same time. our problem is we could not enter the quantity completed for (3)carpentary operation until the previous operations (1 and 2) quantity entered in the system.

How can we solve this problem ?

Thanks & Regards.
Noorul haq.

dmcgrath
19th September 2002, 10:41
You can set the operation overlap percentage to 100%. This allows a subsequent operation to start at the same time as a previous operation.

noorulhaq
19th September 2002, 11:10
Originally posted by dmcgrath
You can set the operation overlap percentage to 100%. This allows a subsequent operation to start at the same time as a previous operation.

Thanks for ur suggestion. Yes, I tried this before I put my question. Still system does not allow me to enter quantity
completed until I enter quantity for the previous operation.
Is there any parameter to be setup. ?
I entered overlaping in the session
tirou2110m000 (maintain routing...)

Please help.

arora.dheeraj
20th September 2002, 07:21
Hi there,

Does it give any message ?
Are the count points defined correctly ?

-Dheeraj

ulrich.fuchs
20th September 2002, 07:34
The problem seems to arise because you are doing independent operations in one production order. Indeed, within a single production order, the operations are to be performed one after another. There is a feature that an operation that has been reported complete will also report complete the previous operations, but that will not help you.

Why don't you seperate the whole thing into three different items / production orders, one for cutting, the other one for woodworks, and the third to put the things together? Since the operations are independent, that is what Baan would expect also from a production planning perspective. Or is that too much overhead?

Uli

noorulhaq
21st September 2002, 09:43
Originally posted by ulrich.fuchs
The problem seems to arise because you are doing independent operations in one production order. Indeed, within a single production order, the operations are to be performed one after another. There is a feature that an operation that has been reported complete will also report complete the previous operations, but that will not help you.

Why don't you seperate the whole thing into three different items / production orders, one for cutting, the other one for woodworks, and the third to put the things together? Since the operations are independent, that is what Baan would expect also from a production planning perspective. Or is that too much overhead?

Uli

hi,

It is too complicated to split in to many production order. Even if we do so, what will happen to the cost of the item.

Please help.

noorulhaq
21st September 2002, 09:55
Originally posted by arora.dheeraj
Hi there,

Does it give any message ?
Are the count points defined correctly ?

-Dheeraj

The system is not allowing to enter the quantity
completed for the operation No. (2) and
It gives message "Maximum quantity completed is 0".


Note : Operation No. 1 qty completed is '0'

How can we enter the qty for operation number 2.

Please advise.

Paul P
23rd September 2002, 11:51
Reading the operation names, I am guessing that following is what happens:
You have metal materials. These metal materials undergo op 1 (cutting) and op 2 (welding)
You also have wood materials. The wood materials undergo op 3 (carpentary)
You then combine the operated metal and wood in op 4 (fabrication)

If that's indeed the case, then you probably should explore the possibility of network routing instead of linear routing. By network routing, I mean

Metal mat'l - (cutting) - (welding) - semi fin A
- (fab) - fin goods
Wood mat'l - (carpentary) - semi fin B

You would have to specify semi finished goods A & B as phantom. That way, the whole thing will still be included inside 1 production order. If you didn't it'd split into 3 orders.

Rgds,
Paul

noorulhaq
24th September 2002, 08:34
Originally posted by Paul P
Reading the operation names, I am guessing that following is what happens:
You have metal materials. These metal materials undergo op 1 (cutting) and op 2 (welding)
You also have wood materials. The wood materials undergo op 3 (carpentary)
You then combine the operated metal and wood in op 4 (fabrication)

If that's indeed the case, then you probably should explore the possibility of network routing instead of linear routing. By network routing, I mean

Metal mat'l - (cutting) - (welding) - semi fin A
- (fab) - fin goods
Wood mat'l - (carpentary) - semi fin B

You would have to specify semi finished goods A & B as phantom. That way, the whole thing will still be included inside 1 production order. If you didn't it'd split into 3 orders.

Rgds,
Paul

Hi paul,

Thanks for ur suggestion.

If I am not wrong, the network routing is possible only for
process item. To define network routing, we need to define
relationship for operation (psrou2120m000) which exist under
routing for process item.

Could u please explain more detail about phantom items.

Thanks.

Noorulhaq

sturla
24th September 2002, 11:37
Regarding Phantom Items, look at:

http://www.baanboard.com/baanboard/showthread.php?s=&threadid=5426

Sturla

Eddy G
24th September 2002, 11:52
Speaking for Paul...:

Only thing you need to do is:
Specify a correct BOM with "EndItem" having materials "Metal" and "Wood", which should be phantoms (!! - flag on BOM-line)

Then in Item - Routings specify the Cutting and Welding operations for "Metal", the Carpenting operation for "Wood" and the Fabricating for "EndItem". So in fact three different routings.

When you create the Production Order for the EndItem, you will get operations like:

10 (Fabricating "EndItem")
/
100 --- 110 (Cutting & Welding "Metal")
/
120 (Carpenting "Wood")

And you are allowed to do the parallel things you would like to do, because the mechanism of reporting quantities on previous operations won't find previous operations anymore for 10, 100 and 120.

Of course still when reporting qties on operation 110, qties on operation 110 will be reported.
And guess you like that.

Regards - Eddy

noorulhaq
24th September 2002, 18:06
Hi Eddy G,

Thanks for ur response. I followed as per ur suggestion. When I create a Production order for 'EndItem' (which has two phantom item in BOM and both has individual operations defined ), the operations for phantom item does not appear in the same production order. It shows only EndItem operation only.

But it brings the sub-components of phantom item under estimated materials which I think is correct.

Is there any parameter settings to get operations of phantom item in the same production order (of EndItem).

Please advise.

Eddy G
25th September 2002, 09:53
Noorulhaq,

No, there is no parameter setting that I know may cause this.

What BaaN version are you on?
- In BaanERP it might be the effective dates...
- Be sure the phantom operations are linked to the right Item.
"Metal" and "Wood", so the phantom items.
- Are these standard to order Items? In that case I think it will try to find the routing of the Derived-from-Item.
- Did you check "Standard Routing" on the Item Routing. If you do so it will retrieve operations from the standard routing specified in stead of the operations you linked to this routing...!

Hope this helps... Eddy

noorulhaq
25th September 2002, 16:45
Eddy G,

We are using BaaN 4c4, WIN NT4, Sql ver 7.

- Yes I checked all the operations defined for phantom items as well as 'EndItem' are correct.

- The order policy of the items (Both 'EndItem' and Phantom items) was 'To Order'. I tried with 'Anonymous' also. But No Luck.

- There was no standard routing defined for any of these items.


Let me explain how I defined routing and phantom items.


Item Master
----------------


Item A - End item
Item B - Metals (Phantom item)
Item C - Carpentary (phantom Item)



Bill Of Materials For Item A are
---------------------------------------------
Item B,
Item C (phantom "yes" for both)


Routing
-----------
Operations

Item A - Fabricating Operations (No. 10)
Item B - Cutting (No.20) and Welding (No.30)
Item C - Carpentary (No.40)

Production Order
---------------------
Item A


Finally, system shows only Fabricating operation(10) and does not show other operations like 20,30 and 40.

Hope it is more clear. Please help.

NoorulHaq.

Eddy G
25th September 2002, 16:58
NoorulHaq,

Ooh... Baan IV. I think this whole concept won' t work in that version.

This (network routings) is new in Baan V (BaanERP).
There besides the "Operation" we also have the "Next Operation". Thus more than 1 operation can have the same "Next Operation". This is what is called a network routing.

So in the example:
10 would have N.O. = 0 meaning it is the last operation.
100 would have N.O. = 110 and
110 would have N.O. = 10 (where phantom routing of "Metal" is linked to the main routing) and
120 is also linked to 10.

So... this might be one of the good reasons to think about BaanERP...?!

Eddy