Tom Waugh
15th August 2002, 04:26
To the Board -
When using the EBOM's and PBOM's I have the follwoing problem:
Assume that assembly P (rev A) consists of parts 1,2,and 3 and if it is modified so that part 2 is replaced by part 4 with rev B on the engineering side and the effective date is set to 45 days from now. The EBOM is released and rolled to the PBOM side. Now part 2 will have a Expiry Date of 45 days from now and part 4 will have a Start Date of 45 days from now. This is all fine until two weeks from now when we need to make a change to this same assembly but now need to replace part 1 with part 5 and make it effective immediately. The system will not allow this next change to be effective before day 46 because of the effectivity of rev B. I cannot unrelease rev B because it has been copied to the production side. Is there a way to handle this problem so that the material planners see the change in the MRP and the engineers can still make other changes as needed?
Thanks
When using the EBOM's and PBOM's I have the follwoing problem:
Assume that assembly P (rev A) consists of parts 1,2,and 3 and if it is modified so that part 2 is replaced by part 4 with rev B on the engineering side and the effective date is set to 45 days from now. The EBOM is released and rolled to the PBOM side. Now part 2 will have a Expiry Date of 45 days from now and part 4 will have a Start Date of 45 days from now. This is all fine until two weeks from now when we need to make a change to this same assembly but now need to replace part 1 with part 5 and make it effective immediately. The system will not allow this next change to be effective before day 46 because of the effectivity of rev B. I cannot unrelease rev B because it has been copied to the production side. Is there a way to handle this problem so that the material planners see the change in the MRP and the engineers can still make other changes as needed?
Thanks