After Master Planning When the session is run to transfer the Confirmed Planned Orders, System gives an error Report saying
" Operation 60 of Item AP39 is not within the Resource's Operation Horizon, Transfer Not Possible"
I tried with various horizon with the max number also!! in the session Resources cprpd2500m000 and also followed by Rebuild Resource session. ( even tried deleting the operation, but the error switched to Operation 50 :) )
Has anyone comeacross this error while Transferring Planned Orders from Master Plan to SFC, If so Pl suggest the procedure to overcome this .....
Thanks in advance
Regards
Sridhar Joshi
Ver: BaaN VC
After Master Planning When the session is run to transfer the Confirmed Planned Orders, System gives an error Report saying
" Operation 60 of Item AP39 is not within the Resource's Operation Horizon, Transfer Not Possible"
I tried with various horizon with the max number also!! in the session Resources cprpd2500m000 and also followed by Rebuild Resource session. ( even tried deleting the operation, but the error switched to Operation 50 :) )
Has anyone comeacross this error while Transferring Planned Orders from Master Plan to SFC, If so Pl suggest the procedure to overcome this .....
Thanks in advance
Regards
Sridhar Joshi