dv3-1028
10th December 2010, 04:03
Hi Guru,

Anyone know what happen if the new Work Center that duplicated from the existing work center and when attached in the routing when running the planning, the operation attached with the new work center is not exist in the planned production order.

Please assist thank you.


Regards,
:confused:

roys11_in
10th December 2010, 13:51
Hi,

Can you please check your item routing once more, sometimes if you change the work center in the routing and tab through, there could be a chance that the machine is not updated in the routing, also be sure about the task, work center and machine relationship (if any was maintained before for old work center).

Regards,
Roy