david.montoya
8th September 2010, 18:50
I have a problem with the planning session Move Plan to planned orders (cprmp2240m000) in Baan 5.0 C since until last week this process assigned to planned manufacturing orders the routing code defined as standard route in ROU parameters ROU but from This week is creating planned orders but the routing code field remained empty .... This prevents me from transfer orders ....

I dpn´t know that can occur if I have not change any settings or configuration. If anyone can help me with this issue would appreciate
==========================================================

Tengo un inconveniente con la sesion de Mover planificacion a ordenes planificadas (cprmp2240m000) en Baan 5.0 C ya que hasta la semana pasada al ejecutar este proceso a las ordenes planificadas de fabricación les asignaba el codigo de ruta estandar definido en los parámetros ROU pero a partir de esta semana está generando las ordenes planificadas pero el campo de codigo de ruta esta quedando vacio.... esto me impide la transferencia de las ordenes....

No se a que se pueda deber esto si no se ha cambiado ningun parametro o configuracion. Si alguien me puede ayudar con este tema les agradeceria.

arun.handoo
8th September 2010, 19:50
Please check solution#808797 on infor365.

Schlingmann
14th September 2010, 15:42
This problem occurs because of the use of time horizons like 9999. Adding 999 to the actual date resolves in an invalid UTC Date. Reduce the horizon in the plan item master data and the ressource or install the appropriate Infor solutions.

Muchos saludos
Jörg