Hi all,
can any one guide me the utilization of order horizon in tpop session (whinh2201m000)? i have tested several scenarios but same is not getting resolved. specially factor field. session help is defining "The factor can be used to make sure that the order will be in time.

:mad::mad::mad:

kmadduri
28th September 2010, 01:12
Suppose you have a lead time of 10 days and a safety time of 2 days. Then if you have a factor of 2, then the system will consider the demand from now till 24 days. If you add a constant of 3, then it will consider 27 days. The constant typically reflects the order processing time and the factor is a multiplication factor on the lead time + safety time. Hope this helps.

Kumar Madduri

asfarjee
5th October 2010, 06:57
Hi Kumar Madduri,
Thnaks a lot.