Approval by Engineering and Approval by Production , do we have to process it ? or can we skip it?
Anyone can explain whats those functions are for and what is the difference between those 2 function.
Since we can not seperate these 2 function by user (no session code ).

Umesh Mittal
31st July 2010, 13:53
Hi,

The steps "Approval by Engineering and Approval by Production" are mandatory so user has to have process it hence these can not be skipped.

quelle
5th August 2010, 05:25
Thanks alot Umesh for your reply.

vishal.upmanyu
14th August 2010, 09:56
Indoubtly the both process are mandatory for a standard business cycle.
the only difference between is that each of them are carried by diferent departments(design & Production) of an organisation which acts as level wise approval for the same Process.