We have implmented PCS/ Projects in BaaN 4c4. Can we treat our semi finished items as "phantom item". We don't want to generate production orders for semi finished items.
Our items structure under each project as follows:-
Finished Goods- Item "A" (Manufactured)
Semi Finihsed - Item "B" (Manufactured) linked as customzed BOM to above finished goods item "A".(Item B we wanted to treat as Phantom Item)
Raw Material - Item "C" (Purchased) linked to above semi finished item "B".
Looking for prompt reply from any one.
Thanks in advance.