dv3-1028
11th June 2010, 10:37
Hi,

My client got 2 production order that need to do sub-con.
However both go to the same sub-con PO.

The status of the production orders shown 'Completed'.

Is there any way to revert this production order status or to separate the subcon-PO to linked to ONE production order ONLY?

Thank you.


regards,

Flip_J
24th June 2010, 12:28
ticst0203m000 can revert Completed to Active.
Available only from FP5 I think

DineshSharma
21st October 2010, 15:11
Hi,

This session revert the status of production order, when it has Closed status.
If the production order has completed status, there is no session avilable for reset the status to active.

Regards

Dksharma

Flip_J
21st October 2010, 15:19
attached is the session

quelle
22nd October 2010, 05:27
only start from FP 5 can revert prod ord status from complete to active.

Raman_baan30
29th October 2010, 10:13
yes this is only available in FP5 not in Fp2 & SP0

Thanx

sudhir
16th December 2010, 13:34
the session is available in FP2, but it does not give option of selection via checkbox

dv3-1028
30th December 2010, 10:53
attached is the session

thanks for the information. :)