Renegade
28th May 2010, 16:42
Am trying to setup new calendar lines wherein a work centre is available only 80% of a workday. So, in Time interval type am setting up "Capacity Percentage"; And Actual Calendar lines shows "Cumulative Time" and "Cumulative Capacity"; Cumulative Capacity is correct (% of total time available); But Planning is not working as per this calendar for this work centre. Am clueless if something else need to be considered too. Any Parameter? Please help. Thanks

Renegade
26th August 2010, 18:06
no replies... but just posting my finding so someone can benefit; Planning does not look at Time interval types' Day percentage or capacity percentage. Neither is it looking at Available time as per Availability type. It sheerly goes by start and end time as in Time interval type and generates calendar line which gets converted to Actual Calendar.

sdvries
31st August 2010, 15:23
The capacity percentage is only used in the planning of the routing operations. Make sure that the availability type and calendar in Routing are correct.

The other lead-times, like safety time, inbound, outbound etc are not using the capacity percentage.