Hi,
If I have put 100pc. in forecast for 1st week of month, 1) It should give me planned production order for 20 coz. my production capacity is 20pc. for per day, 2) Production start dated should be 5 days before coz. I need 5 day to production.

Please advice me where are interlinks.

Thank you,

Regards,

rohit_367
25th March 2010, 08:37
You can use work load controll to generate Planned Production Order.
For WLC use following steps
WLC Implemented in parameters
Plan unit of WLC linked to your iten in Item Planning Master Data.
Generate Master Plan with Material & Capacity constraints.
It should work