jimouyang
22nd March 2010, 08:28
how to do the setting for two planned production orders overlap.

In one prodution order, setting the transfer batch in routing for different operations can handle it. However, how to do the similiar setting for different planned prodution orders.

thank you -jim

quelle
25th March 2010, 03:52
Hi jim, u can check resource order plan to check over lap for planned production orders in 1 work center, but still need to adjust it manually.