abby13
5th March 2010, 07:12
Hi All,
For a particular actual scanario that has been initialized, we have a plan item which has a sales order of 200 pcs existing. When i put a forecast of 300 for that period and run the item master plan it is expected that it should create a production plan for 300-200=100 qty. However it does not create a production plan. in the plan items session (Master Plan tab), the Production pan is set to 'Always update'.
Is there any additional setting for the production plan to be updated?
Regards
Abhijit.
For a particular actual scanario that has been initialized, we have a plan item which has a sales order of 200 pcs existing. When i put a forecast of 300 for that period and run the item master plan it is expected that it should create a production plan for 300-200=100 qty. However it does not create a production plan. in the plan items session (Master Plan tab), the Production pan is set to 'Always update'.
Is there any additional setting for the production plan to be updated?
Regards
Abhijit.