chingi
14th December 2009, 14:30
Hi All,

While exeucting session 'Generate planned MRP orders (timrp1210m000)' I got following message.

'Actual calendar not found when planning (Backward) for work center on 23-07-2010 with 0 time units of planning time'.

Do not know which calendar is missing.

Please let me know if any one can give some inputs.

bdittmar
14th December 2009, 16:11
Hi All,

While exeucting session 'Generate planned MRP orders (timrp1210m000)' I got following message.

'Actual calendar not found when planning (Backward) for work center on 23-07-2010 with 0 time units of planning time'.

Do not know which calendar is missing.

Please let me know if any one can give some inputs.

Hello,

check the company calendars with tirou4101m000 !

Regards