cherokee
20th November 2009, 22:07
Hello everyone,

I've moved my Reference Date for my MPS Plan Code. I used to have starting day of the week on my schedule on Sundays, now after running my MPS, I have Wednesdays as start day of the week... I do not want this happen. I have changed the Start and Reference dates before in my MPS Plan Code serveral times and this is the first time that I have my Schedule week day starts on Wednesdays.

Can anyone give me a hand?

Thanks,

avpatil
25th November 2009, 15:54
It all depends on the buckets- Maintain Plan period. That will determine the start date. Aren't you able ot change the plan period?

Arvind Patil

cherokee
25th November 2009, 20:15
Yes, I changed my plan periods as follow:
Up to Date Period Length
31-01-2010 7 which is Sunday
04-04-2010 28 Also Sunday
30-03-2011 84 Wednesday

I'll check the last period(84).

avpatil
25th November 2009, 20:39
What is the MPS plan start date?
31-01-2010

If it is a rolling plan then the system will start rolling from its start date. I have never found a rolling plan useful. I always defined a static plan, and then keep on changing the mps end date and the mps plan period thru a program.

Arvind