19th November 2009, 11:33
Hello,
does somebody know something more about module planning in LN? I mean something more else in "help" wrote is.
Or something about planning of material for PCS Projekt internally? Without sales order...
Thanks
T.
sykomike
19th November 2009, 16:31
The help file leads you down a certain path but I can't make it work. I hope you have better luck than I did
sykomike
20th November 2009, 19:37
"
You can define modulesfor projects in the Project Control (PCS) module in BaanERP Manufacturing.
If you select the Fixed Plan Quantity check box in the Module Planning (tipcs4520m000) session, you can
enter the required quantity directly in the Plan Quantity field. If you clear the Fixed Plan Quantity check
box, BaanERP determines the required quantity based on the BOM.
BaanERP determines the date of the requirement on the basis of the network planning in the Project
Control (PCS) module.
If you plan a customized item with order-based planning , the plan quantity of the module is the basis for the
generation of planned orders.
If you want to generate orders on the basis of the module planning, the item must have an item master
plan. You must not use this master plan for master-based planning; the master plan is only used to
temporarily store the requirements.
If you transfer planned orders from Baan Enterprise Planning to the execution level , BaanERP
automatically reduces the plan quantity in the Module Planning (tipcs4120s000) session by the order
quantity, so that you can plan the remaining plan quantity during a following RRP calculation."
I just nver see the results transfer to item master plan or time phase. that is the result I am expecting.