Dear All,

I made Multilevel product structure of finished item which contains 3 manufactured item

Setting :In INFOR LN FP5

Order Policy :To Order

Order System : Planned ( for all items)

By Running order planning then in Planned orders session it shows only main item planned production order whereas it should show us 4 planned prd orders & purchase orders.

Can anybody tell me where is i am lacking (parameters)

Thanks & Regards,

Sandip

quelle
28th October 2009, 11:59
the finished item is manufactured item and consist of 3 manuf item too?
so theres should be 4 planned production order right?
have you check the topdown selection?
also make sure theres no standard item inventory for the other 3 .
If theres any inventory, then you have you unlink derived item in item general-(tab engineering).

s_amrutkar7
4th November 2009, 20:54
Thanks for your reply,


I already got answer during search for this & find same as you answer.


Thanks & Regards,

Sandip