Is BaaN Planning System capable of handling pull in and pull out of job orders?

This scenario happens to us when the customer requests to expedite an order.

sturla
1st July 2002, 00:50
If you change the delivery date at the sales order line for a MRP item, you will get a rescheduling message that tells you to reschedule existing SFC-orders (or other kind of ordres). The change in planning of the order have to be done manually in standard Baan (it's possible to make customizations to do resceduling / replanning automatically).