I am trying to transfer "planned production orders" to the execution level, i.e., When I transfer them through cppat1250m000 LN displays the following message:
"the number of operations differ from the number present in routing operations (also check resource storage horizon)".

If I created production order manually, then the system is not giving any error message.

Do you have any idea how to do it ??, your quick reply in this regard will helpfull to me ......

Thanks

mprakash
9th August 2009, 09:13
In this case you have to replan the planned order and then make the transfer. you can also delete the existing planned order and simulate the item again to get the fresh order and then transfer to shop floor. There might be change in the standard routing and it will not match with the capcity used in the planned order.