15th June 2009, 10:50
Sir/Madam
In session tisfc0202m000 by mistake I have marked the status of a PO as Completed.
How do I change this to Released status.
Regards
Django
jayverma25
30th June 2009, 15:27
In BaaN IV option is not available to change status from completed to active(In LN6.1 FP5 option is available to change the production order status from completed to active). You have to create new prod order & report order quantity againest same.
avpatil
6th July 2009, 15:50
The effect of changing the status to "Complete" is that it removes any planned transactiom of main item and also delete the transaction from tisfc010.If you want to change the status back to Release, you will need to do through Table maintenance and add the transaction in tdinv150 and on order qty in tiitm001, and tdinv001 appropriately.
Arvind Patil