drawat69
16th February 2009, 12:39
Hi,

We are getting Planned Receipt and Schedule Receipt 1 day prior to customer order schedule afer running the MPS.

What could be the possible reason for so. ?
How to solve the issue.
Enclosed screen shot for the item and its planned.

Thanks and regards
Dev.

avpatil
18th February 2009, 10:18
It is not exactly one day. If you can see system combined the demand of 21/02 and 22/02, while it choose to generate the planned receipt on the day of demand on 23/02. It may be doing due to order interval. Also, if you have set up forecast consumption foward or backward this also happens, biut since you don't have forecast, so this is ruled out.

When running the MPS say on 21/02 gibe the MPS genration date as 20/02 and see if the results varies.

Arvind Patil

kasey31
19th February 2009, 11:12
Safety time of 1 will also change the end date

drawat69
20th February 2009, 05:44
Hi,

Thank you very much for your input.

Problem resolved when I run the session tirou4204m000 (create default company calender).

Thanks and regards
Dev.