We have the following scenario:
Part P1 has Part C1 in its BOM.
Part P2 also has Part C1 in its BOM.
Part P1 needs to be manufactured in Warehouse W1 and Part P2 needs to be manufactured in Warehouse W2. I have one production order for P1 and another production order for P2.
When I run Simulate Orders, I am looking for 2 planned purchase orders: one to be reecived in W1 and the other to be received in W2.
How would I accomplish this? Thanks in advance.
Part P1 has Part C1 in its BOM.
Part P2 also has Part C1 in its BOM.
Part P1 needs to be manufactured in Warehouse W1 and Part P2 needs to be manufactured in Warehouse W2. I have one production order for P1 and another production order for P2.
When I run Simulate Orders, I am looking for 2 planned purchase orders: one to be reecived in W1 and the other to be received in W2.