kw_foo
7th June 2002, 09:00
Hi,
The following is the procedure that I tried to generate the CRP but failed:
1. Execute the "Generated MRP"
2. Check and found records with "MRP production batches" in session "Display Planned Inventory Movements by Item".
3. Run session "Plan Production Orders/Batches (CRP)"
4. Check the inquiries sessions in the Capacity Requirement -> Inquiries menu but all of them are showing empty, no record generated.
Can somebody advice on the steps, or the settings that might cause this problem ??
Please advice.
KW Foo
The following is the procedure that I tried to generate the CRP but failed:
1. Execute the "Generated MRP"
2. Check and found records with "MRP production batches" in session "Display Planned Inventory Movements by Item".
3. Run session "Plan Production Orders/Batches (CRP)"
4. Check the inquiries sessions in the Capacity Requirement -> Inquiries menu but all of them are showing empty, no record generated.
Can somebody advice on the steps, or the settings that might cause this problem ??
Please advice.
KW Foo