Dear All
In sub contracting, every time company sends all tools outside the premises also it adds tooling cost of subcontracting. When material like Jigs, fixtures etc to be sent out how to be mapped this in the system?
Shall i add new operation of for sending and raise subcontracting item for that and collect material against the same or is there any different method?
Can I encorporate inspection? As far as I know it cannot be.
Please help me
Thanks in advance