BOBBYLYON
17th October 2008, 11:58
In ERP LN 6.1 FP1 (soon moving up to FP3...), under “Machines” (tirou0102m000) and “Routing Operations” (tirou1102m000) sessions, is this possible to setup/select several machines for/ against one only one operation?
If so, could someone please explain how to setup this up..?
Thank you :confused:
Bertrand
nishant
18th October 2008, 06:17
HI,
You can't define several machines againest one and one operation..... What u can do is maintain more than operation say 10,20,30 with the same TASK & same W/C but with the different MACHINES.
Eg.
Operation10- TASK1,W/C1------MACH1
Operation20- TASK1,W/C1------MACH2
Operation30- TASK1,W/C1------MACH3
May be ths will help u in mapping ur requirement.
Regards
Nishant
nishant2180@gmail.com
joemon
18th October 2008, 09:00
As per Nishant Explanation U can Use Multi Task Relationship the Same Task & Same Work center But Different Machines
For Exp:- Task A,
Work center B
Machines Z1,Z2& Z3
You’re Task Relationship Are:- (1) A, B, Z1
(2) A, B, Z2
(3) A, B, Z3
I think ur Issue is Slove....
Joemon.V.J
Joemon.vj@gmail.com
BOBBYLYON
20th October 2008, 10:07
Thank you to you both, you have confirmed my assumptions..
Take care,
Bertrand