Bryan
5th December 2001, 00:51
I am building to order and buying to forecast. I have 4 weekly buckets, and 2 monthly buckets
End Item A consists of purchased component B. Lets say I the following a forecast for item A:
WEEk1 WEEK2 WEEK3 WEEk4 MONTH MONTH
10 20 30 40 100 200
For Item A, I have a forecast time fence of 2 weeks.
So, when I generate MRP I will get a planned order for 30 on the last day of week3, an order or 40 on the last day of week 4, an order for 100 on the last day of month1, and an order for 200 on the last day of month2.
The problem here is (for example) week 3...I will build 30 by the last day of week 3....but the forecast I entered says that I need 30 throughout the entire week...not by the last day. This
causes late shipments
My lead time for Part B is 2 weeks, so when I generate MRP for Item B I will get the planned orders:
a planned order for 30 on the last day of weeks, an order or 40 on the last day of week 4, an order for 100 on the last day of month1, and an order for 200 on the last day of month2.
Again, for the order for 30 due to start 2 weeks before the last day of week 3, this means item B will be scheduled to arrive the last day of week 3...when I need it to arrive the first day of week 3 to supply Item A's production throughout the week....
How can I solve this? Basically what I am trying to do is change the requirement day to the FIRST day of each bucket, instead of the LAST
End Item A consists of purchased component B. Lets say I the following a forecast for item A:
WEEk1 WEEK2 WEEK3 WEEk4 MONTH MONTH
10 20 30 40 100 200
For Item A, I have a forecast time fence of 2 weeks.
So, when I generate MRP I will get a planned order for 30 on the last day of week3, an order or 40 on the last day of week 4, an order for 100 on the last day of month1, and an order for 200 on the last day of month2.
The problem here is (for example) week 3...I will build 30 by the last day of week 3....but the forecast I entered says that I need 30 throughout the entire week...not by the last day. This
causes late shipments
My lead time for Part B is 2 weeks, so when I generate MRP for Item B I will get the planned orders:
a planned order for 30 on the last day of weeks, an order or 40 on the last day of week 4, an order for 100 on the last day of month1, and an order for 200 on the last day of month2.
Again, for the order for 30 due to start 2 weeks before the last day of week 3, this means item B will be scheduled to arrive the last day of week 3...when I need it to arrive the first day of week 3 to supply Item A's production throughout the week....
How can I solve this? Basically what I am trying to do is change the requirement day to the FIRST day of each bucket, instead of the LAST