s_amrutkar7
29th September 2008, 08:02
I am working on LNFP2. I have one Scenario of workshop as per following:

Workshop department manufactures new mould assembly by using mould box,setting plates,Liners & Dies according to requirements. Mould is prepared according to production schedule & transferred to press department on requisition. As mould life expires it is send back to the workshop for rework where mould is disassembled & rework is done on liners i.e. regrind with the help of surface grinder. Same thing is happening for Dies also then mould is again assembled & sent to the production department.

Note: Mould box, die block -- purchased
Liners,Dies,Setting plates -- Manufactured

Can Anyone Suggest As is mapping for this scenario in lnfp2.

seenivasank
1st October 2008, 20:48
Hi,

Try for Tools Requirement Planning (TRP) along with Service Order Control.

Regards,

Seenivasan

s_amrutkar7
2nd October 2008, 11:08
We are not implementing Service & TRP Modules so can anybody suggest possible solution for this scenario in LN.