Does anyone know on what basis Baan calculates the requirement start date and req. finish date in Rough material planning session timps4510m000.
i am also having problems generating rough materials req for the live plan. It generates for the simulated plan!!!

can someone provide inputs here

thanks

bhaswar

vavs123
29th May 2002, 23:22
I am having some problems with rough cut planning as well. Here is what I have learned. Rough cut material is generated from the bill of critical materials. It uses the lead time offset (pretty sure ) to determine start and end dates on manufactured items. It is automatically calculated if you answer yes to the filed Generate Rough Material Requirements. I am having a problem with it not recognizing the expiry or effectivity date of the items based on the planning periods. As to why it is generating the rough cut material for your simulated plan, double check the MPS parameter settings. Make sure your simulated plan is not listed.