riazsayeed
25th June 2008, 08:54
Dear Friends,
In a Subcontracting Purchase order,instead of receiving 300,000 Pcs, our warehouse received total order quantity 600,000 Pcs by mistake. How do I returm this back? I am unable to correct the receipt line.
Any help would be highly appreciated.
Thanks
VishalMistry
27th June 2008, 10:52
As long as I know. There is no simple of returning against subcontract receipt. You can not create return PO for subcontract items. The only way I think is creating production order for the quantity you wish to receive from supplier and again generate subcontract purchase order.
looking from accounting point of view, you have to pass a debit note entry.
Vishal
riazsayeed
28th June 2008, 11:17
Hi Vishal,
If I create a production order again and it generates a positive PO again, how can I relate this to the earlier production order costs. I thought of rework order as well, but I guess this will also not work.
Nileshp
18th July 2008, 09:17
hi
RT now donno wht can be done, need to simulate, but we can surely prevent transaction in future. in item purchase qty tolerance and hard stop on quantity select block....
I f u have solved u r query just update us...
Allah Hafis
Nilesh