tnzabo
10th June 2008, 22:41
Hello - I'm wondering if someone could educate me on when/how estimated costs get to the tipcs360 table. I have many projects that don't have estimated costs in this table however, if I were to look at the single items or production orders there are estimated costs on them. We run the tipcs3250m000 Calculate Cost Prices by Project nightly for all projects. The Perform Estimated Cost Price Calculation flag is set to yes. Any ideas?
thanks - tnzabo