qiangyao
5th June 2008, 09:50
Order status is
Planned
Firm planned
Confirmed
I would like to know more details and How to use?
Thanks
alexlow
5th June 2008, 14:01
if the status is confirmed, than you can transfer your plan purchase order or production order to the actual one.
i have another question also, if anyone knows please advice, is there any way to keep track the history of planned order after been transfered?
thanks
hexagenia
9th June 2008, 16:12
You can transfer all three to production / purchase / distribution.
You can determine if Firm Planned gets rescheduled at next planning run or not. Planned orders always do.
You can detremine how Firm Planned gets rescheduled...for instance...do I schedule a new Planned order before an existing Firm Planned order when I rerun planning?
Baan / LN functionality is consistent with basic APICS / MRP functionality. I would purchase an APICS dictionary as a starting point and then move onto more detailed texts if you still have interest.
hexagenia
9th June 2008, 16:13
Tracking of released planned orders might be addressed by pegging functionality in ERP LN.