vick.chung
30th May 2008, 07:55
hi all,

do anyone know where can i input a factor (other than scrap factor) to be calculated into the planned purchase order.

The formula should be: net qty * (1+scrap factor) * (1+purchase factor)

thx.

csjoshi
4th June 2008, 13:44
Hi:
Have you tried 'Yield' functionality instead?

vick.chung
5th June 2008, 04:23
thanks, i 've tried the yeild in routing opertion tirou1502m000, it increases the order qty of the parent item but i just want to increase the planning qty in material level only.

csjoshi
5th June 2008, 07:27
you write a customization, which could increase the planned purchase order quantities by the factor you want.